Background: Component Shortage Report
Use the Component Shortage Report (MOSL) program to print a report that shows manufacturing orders that were released with a component shortage or could not be released because of a shortage of components. See Road Map for work flow.
If you release or attempt to release an order that has a shortage with the Order Release Selection (MRR) program, that program launches the Component Shortage Report. If you run this report from the menu, the reports shows the shortages from the last time that you ran the Order Release Selection program.
The report includes this information if you sort by component:
Component number
Component description
Buyer
Planner
Remote branch
Parent item number
ECL (engineering change level)
Parent item description
The report includes this information if you sort by parent item:
Parent item number
ECL (engineering change level)
Parent description
Component number
Component description
The report includes this information regardless of the sort order:
Order type: PLN: Planned order, REQ: Requisition
Rel: Y: Released, N or blank: Not Released
Order number assigned to the released order
Due date
Quantity required
Quantity available: Quantity on hand - Quantity committed
Quantity on hand
Soft?: Y: Order was not released due to shortage, N: Order was released despite shortage
If you selected the Show purchase orders? Program option and purchase orders exist, the report includes this information:
Purchase order number
Line number on the PO
Vendor number
Vendor name
Date wanted
Date promised
Quantity ordered
Quantity received to-date
If you selected the Show manufacturing orders? Program option and manufacturing orders exist, the report includes this information:
Manufacturing order number
Due date
Quantity ordered
Quantity received