Background: Project Summary Listing
Use the Project Summary Listing (PSL) program to print cost details of each project quantity and optionally, the bill of material and routings. See Road Map for work flow.
The Project Summary includes this header information:
Project number
Branch
Status of project: N: New, C: Closed, T: Transferred
Engineering Change Level
Project entry date
Customer number for a customer project
Parent item number
Routing Revision Level
Project expiration date
Customer name for a customer project
Parent item description
Stocking unit of measure
Customer's project number
Requester
User-defined project status
Pricing factors
Percent of total factory cost
Amount added to order
Amount added to each unit
Percent of material cost
Percent of labor cost
Other user-definable percentages
Amount added to total
Note
Your fields may have a different labels based on your entry in the User description field for each
project code in the Project Cost Factors Maintenance (TPS) program.
Default rates
Labor rate
Overhead rate
Machine rate
Setup rate
Project notes is you selected Include project notes? program option and notes exist
Project quantities (listed by quantity breaks if they exist)
Project quantity
Material cost
Labor cost
Overhead cost
OS cost: Outside service
Total factory cost
Miscellaneous costs
Percent of total factory cost: (Percent of total factory cost / 100) x Total factory cost
Amount added to order
Amount added to each unit
Percent of material cost: (Percent of material cost / 100) x Material cost
Percent of labor cost: (Percent of labor cost / 100) x Labor cost
Total cost of sale: Total factory cost + Misc costs + % of total fact cost + Amt added to order + Amt added to unit + % of matl total + % of labor total
Profit percent: (Profit percent / 100) x Price less discount
Commission percent: (Commission percent / 100) x Price less discount
User-defined percents: (User-defined percent / 100) x Price less discount
Base price: Total cost of sales + Profit percent + Commission percent + User-defined percents
Discount %
Discount amount: (Discount % / 100) x Base price
Price less discount: Base price - Discount
User-defined fixed amount
Final price: Price less disc + Fixed amount
Unit price: Final price / Project qty
If you selected the Include routing listing? Program option, the listing includes this information for the routing header:
Item number
Customer item number
Customer reference
Item description
Manufacturing lead time
Material code and description
Routing Revision Level
Date entered
Date changed
Standard lot size
Average lot size
Maximum order quantity
Rough weight
Processing unit of measure
Total hours per piece for all operation sequences
Total hours per lot: Run per unit x Standard lot size
Setup time
Total run time: Run time per lot + setup time
Header notes if you selected H or B for the Include routing notes? Program option and the header notes exist
The listing includes this information for each operation sequence:
Operation sequence
Operation type: R:Regular, B:batch, I:Indirect, P:Purchased service, U:Unattended
Work center number
Operation description
Set up time
Pieces per hour
Setup labor code
Setup labor rate
Processing unit of measure
Department number
Operation sequence type: S:Standard or A:Alternate
Send ahead quantity
Operation code
Machine number
Tool number
Operation pieces per hour:
For a regular or unattended operation: Pieces per hour x UOM conversion
For a batch operation: Hours per batch
x UOM conversion
Hours per piece
Direct labor code
Direct labor rate
Unit of measure conversion factor
Crew size
Move time
Cost per piece for a purchased service operation type
Line notes if you selected L or B for the Include routing notes? Program option and notes exist
If you selected the Include BOM listing? option, the BOM listing includes this information:
Parent item number
Engineering Change Level
Number of levels you entered for the Select number of levels for BOM Program option
Lead time for the parent item: Order prep lead time + Manufacturing lead time
Accumulated lead time
Item description
The listing includes this information for each component
Header notes if you selected H or B for the Include BOM notes? Program option and notes exist
Level in the bill of material relative to the parent item
Component number
Processing unit of measure
LT offset: The number of days after a manufacturing order is released that this component is required
Lead time for this component:
For an item you make: Order prep lead time + Manufacturing lead time
For an item you buy: Order prep lead time + Intransit lead time + Put-away lead timeQuantity per parent item
Scrap percent of this component expected during manufacturing
Effective date: The date from which the component is used for manufacturing orders
Expiration date: The date after which the component is no longer be used for manufacturing orders
Floor stock code
0: Not floor stock
1: Floor stockBypass code
0: Finished good or dependent item (component)
1: PhantomComponent type: User-defined
Description of the component
Substitute item for this component
Reference code
Part designator
M/B/K: M:Make item, B:Buy item, K:Kit item