Display Cost Rollups
When you click CRU history in the Item Cost Inquiry (ICQ) program, these fields display:
|
Field Name |
Displays |
|
Date/time stamp |
The date and time on which the cost roll up occurred |
|
New unit cost |
The rolled up unit cost after the cost roll up |
|
Old unit cost |
The unit cost before the cost roll up |
|
User |
The person who performed the cost roll up |
-
Select the rollup you want to display and click Select.
The program displays these fields:
|
Field Name |
New |
Old |
|
Standard matl cost |
The total material cost after you updated it |
The total material cost before you updated it |
|
Standard lbr cost |
The total labor cost after you updated it |
The total labor cost before you updated it |
|
Standard ovhd cost |
The total overhead cost after you updated it |
The total overhead cost before you updated it |
|
Standard OS cost |
The total outside service cost after you updated it |
The total overhead cost before you updated it |
|
Unit cost |
The unit cost after you updated it; unit cost is the sum of the standard material, labor, overhead, and outside service costs. Unit cost is also called standard cost. |
The unit cost before you updated it |
|
Incr matl cost |
The incremental material cost after you updated it |
The incremental material cost before you updated it |
|
Incr lbr cost |
The incremental labor cost after you updated it |
The incremental labor cost before you updated it |
|
Incr ovhd cost |
The incremental overhead cost after you updated it |
The incremental overhead cost before you updated it |
|
Incr OS cost |
The incremental outside service cost after you updated it |
The incremental outside service cost before you updated it |
An asterisk (*) displays to the right of fields in the New column that are different from the equivalent field in the Old.
The program displays these fields:
|
Field Name |
Displays |
|
Qty on hand |
The quantity of this item in stock at the time of the last update |
|
Zero costs only? |
Selected: this cost rollup includes only items that do not yet have an accumulated cost; the program takes into account the costs of components only one level below the zero-cost items. |
|
Multi/Single level |
M: rolled up costs to the parent item of components one level below the parent on bills of material |
|
Dflt labor rate |
The rate used only if the labor code for the routing does not have an associated rate |
|
Dflt ovhd rate |
The rate used only if the overhead code for an item in the Item Cost Maintenance (ICM) or Work Center Maintenance (WCM) programs does not have an associated rate |
|
Product subclass |
The product subclass selection option used for the cost roll up |
|
Product class |
The product class selection option used for the cost roll up |
|
Preferred vendor |
The preferred vendor selection option used for the cost roll up |
|
Date instigated |
The date of the cost roll up |
|
User ID |
The user ID of the person who performed the cost roll up |
|
Calling program |
The program that performed the cost roll up |
|
Problems found |
Any problems that occurred during the cost roll up |
|
ECL |
The engineering change level |
|
RRL |
The routing revision level |
|
GL journal |
The general ledger journal name |
|
Journal posted |
The date posted to the general ledger |
-
Click OK to return to the list of rollups or click Quit to exit and return to the menu.
-
Choose the appropriate options when you click OK:
|
To |
Do This |
|
Display the selected cost rollup |
Click Select. |
|
Display cost rollups from a specific date and time |
Click Restart. The program prompts Date updated and Time updated. Enter the data for the first date you want to display or leave the fields blank to begin the display with the first record in the file. |
|
Print the rollup listing |
Click Print. See Print. |
|
Display the previous set of records in the file |
Click Page up. |
|
Display the next set of records in the file |
Click Page down. |
|
Exit the cost rollup display |
Click Exit. See Display Item Costs. |
|
Exit and return to the menu |
Click Quit. |