Move the Date of a Planned Order

When you select a planned order and click Move in Planned Order Maintenance, you can change the date of a planned order.

  1. Change at least one field:

Field Name

Type / Max Length

Action / Description

ECL

Optional
4 alphanumeric

Accept the displayed ECL or enter a different Engineering Change Level.

Due date

Required
10 date

Select the due date, enter a date shortcut, or press Enter and click Cancel to exit. The due date you select must be on the shop calendar.

Mfg order firm

Optional
1 character

Select F if this order is firm or leave blank if you want the planning system to cancel or reschedule this order based on demand.

  1. Enter data in these fields:

Field Name

Type / Max Length

Action / Description

Start date

Required
10 date

Accept the displayed start date, select a different start date, or enter a date shortcut. The start date must be a work date on the shop calendar.

Qty ordered

Optional
11 numeric

Accept the displayed quantity or enter a quantity.

Routing rev lvl

Optional
4 alphanumeric

Accept the displayed routing revision level or enter a different RRL.

  1. Click OK to return to Planned Order Maintenance.