Background: Accumulated Lead Time Calculation
Use the Accumulated Lead Time Calculation (MLT) program to calculate critical-path lead times for parent items in bills of material and print a report. See Road Map for work flow.
Note
This program does not update lead
time for configured products.
This topic has these subtopics:
Types of Lead Time
Calculating Accumulated Lead Time
Accumulated Lead Time Report
Types of Lead Time
You can specify several lead times for each item in the Branch Item Maintenance (IMB) program:
Lead Time Type |
Field |
Definition |
Manufacturing |
Mfg LT |
The number of days required to manufacture the item from its next level components |
Order preparation |
Order prep LT |
The time required to prepare a manufacturing order or purchase order (for example, the time needed to get approval and process paperwork) |
Delivery |
Intransit LT |
The number of days required after an order is placed with a vendor for the item to be delivered |
Stocking |
Put-away LT |
The time it takes after you receive a item to put it into inventory (for example, to move it to its primary bin location) |
Calculating Accumulated Lead Time
Accumulated lead time is the total the number of days required to manufacture or procure an item, including the time to purchase and manufacture all of its components on a multi-level bill of material.
The value of the LT update field (maintained in Branch Item Maintenance) determines how the item's accumulated lead time (Accumulated LT in Branch Item Maintenance) is updated:
E Exclude queue and move times
Calculates the longest lead time of all components on the bill of material, ignoring the queue and move timesI Include queue and move times
Calculates the longest lead time of all components on the bill of material plus the queue days for the work center that is set up in the Work Center Maintenance (WCM) program and move days for all operations for this item's routing set up in the Routing Maintenance (RTM) programN Do not update accumulated LT
The item's item's accumulated lead time is not updated by the Accumulated Lead Time Calculation (MLT) program
If an item's LT Update field is I or E, the Accumulated Lead Time Calculation program calculates the accumulated lead time based on whether you make or buy the item. If the Make/Buy/Kit field in the item's record in the Enterprise Item Maintenance (IM) program is set to:
If Make/Buy/Kit is |
Includes these lead times |
M Make |
Manufacturing, order preparation and put-away |
B Buy |
Order preparation, intransit, and put-away |
K Kit |
Lead times are not utilized for kits. Kit components have the same due date as the kit parent's expected ship date. |
If the Make/Buy/Kit field is blank and the item has a low level code greater than one, the system considers it to be a Make item.
The LT Update field must be set for the parent item and for every component on its bill of material.
Beginning at the lowest level of a bill of material, the program takes into account the individual lead times of each component item. It calculates a critical-path lead time for each parent, then accumulates these lead times through successively higher levels. Finally, the program updates the Accum LT field in the Branch Item Maintenance (IMB) program.
For example, suppose that you have parent item 1-123 with components 1-1, 1-2, and 1-3 and these lead times.
Item |
Make/Buy |
Mfg LT |
Order prep LT |
Intransit LT |
Put-away LT |
Accumulated LT |
1-1 |
B |
|
0 |
1 |
0 |
1 |
1-2 |
B |
|
2 |
90 |
1 |
93 |
1-3 |
M |
1 |
1 |
|
|
2 |
1-123 |
M |
2 |
1 |
|
|
96 |
For components, accumulated lead time depends on whether you make or buy the item. Accumulated lead time is a sum of the relevant lead time fields. For the parent item, accumulated lead time is the longest lead time of a component (in this example, item 1-2 with 93 days) plus the accumulated lead time for the parent item itself (Mfg LT + Order prep LT + Put-away LT, which in this example is 3 days).
Accumulated lead time sets the time fence for planning programs.
Accumulated Lead Time Report
While updating accumulated lead times, the Accumulated Lead Time Calculation program prints a log of changes. Furthermore, the program offers the option of printing a log of proposed changes without actually changing accumulated lead times.
The report includes this information:
Branch
Item number
Engineering Change Level
Item description
MBK: M: Make, B: Buy, K: Kit
Quantity currently on purchase or manufacturing orders
For a parent item: If a make or kit item: Order prep LT + Mfg LT + Put-away LT for the parent; if a buy item: zero
Order prep lead time
Intransit lead time
Manufacturing lead time
Put-away lead time
Accumulated lead time before you ran the program
Accumulated lead time after you ran the program
LTI: The setting for the LT update field in the Branch Item Maintenance (IMB) program:
I:
Include the queue time for the work center set in the Work Center Maintenance (WCM) program and move time for the operation from the Routing Maintenance (RTM) program: Longest lead time of components on bill of material + Queue days + Move days
E:
Longest lead time of components on bill of material
Blank:
No calculation