Background: PO Receipt Register
Use the PO Receipt Register (VRJ) program to print a list of received purchase orders and update them to the general ledger if you have inventory interfaced to the GL. See Overview: Interfacing Inventory to GL and Road Map for more information.
The system updates actual and average item costs when you receive items into inventory. Therefore, you do not need to run this register after each receipt. You may want to run the register at month end.
Note
If you change the unit cost or GL on a purchase order that has been received
and subsequently reverse the receiver, the program uses the original values
for the reversal.
When you print the PO Receipt Register, these documents print in this order:
Seq |
Document |
Comments |
1 |
Preview register |
Review to be sure that it is correct. |
2 |
Preview journal |
If these options are selected:
|
3 |
Final register |
If this option is selected:
|
4 |
Final journal |
If these options are selected:
|
The register includes this information:
Receiving branch
Receiver number
Receiver line number
Item number
Date received into stock
Quantity received
Stocking Unit of Measure
Standard unit cost for this item in base currency
Extended amount: Quantity received x Standard unit cost) - (Quantity rejected x Standard unit cost)
This amount is .00 if the item is awaiting inspection and negative if you reversed this receiver.PO number
PO line number
Item description
Quantity rejected
Engineering Change Level
Rejected amount: Quantity rejected x Standard unit cost
Reversed if you reversed this receiver
Totals for extended amount and rejected amount in base currency