Background: Manufacturing Order Close
Use the Manufacturing Order Close (MJC) program to close costs for manufacturing orders, print the Manufacturing Order Close Register, and update the general ledger if you have inventory interfaced to the GL. See Overview: Interfacing Inventory to GL and Road Map for more information.
This topic has these subtopics:
| Scrap | |
Completed Orders
The program lists manufacturing orders that are eligible for closing. If you selected the Inventory interfaced to GL? option in the System Options Maintenance (XM) program (Inventory Control Options), all registers must be run.
The program does not list orders if:
Work in process data is incomplete
Labor entries are incomplete or that is a pending labor import batch
Items are awaiting inspection or inspected items are awaiting Material Review Board disposition
A requisition or purchase order that is supply for a manufacturing order has not been received
Associated sales shipments are incomplete
Run the Manufacturing Order Close Preview Report (MJP) program to determine the reason a manufacturing order is not listed.
Preview and Final Register
The register closes costs for the orders that you select and moves the orders to history.
When you print the Manufacturing Order Close Register, these documents print in this order:
Seq |
Document |
Comments |
1 |
Preview register |
Review to be sure that it is correct. |
2 |
Preview journal |
If these options are selected:
|
3 |
Final register |
If this option is selected:
|
4 |
Final journal |
If these options are selected:
|
Register Header
The register includes this header information for each order:
Manufacturing branch
Manufacturing order number
Parent item number
Order due date
Quantity ordered
Quantity completed and received into finished goods
Quantity scrapped
Date picked
Value of completed item: Quantity complete x Standard unit cost of parent item
Order status:
Complete |
The quantity ordered has been received into on-hand inventory |
Closed by rcv |
Received less than quantity ordered and clicked Close order? in the Receiver Maintenance (IRC) program |
Closed by user |
User clicked Close order in the Manufacturing Maintenance (MIM) program |
Parent item description
Engineering Change Level
Routing Revision Level
Product class
Inventory account code
Manufacturing order type
Total complete value for all orders
Stock Material Detail
If you selected the Include stock material detail? Program option, the register includes this information:
Item number of the component
Quantity required: (Quantity ordered x Qty per assy) + (Quantity ordered x Qty per assy x Scrap % x 0.01). Fractional quantities are rounded up to the next integer (e.g., 23.001 becomes 24).
In the discussion below, this is referred to as Original quantity required. If the quantity per at the time of order release is zero (i.e., the item was added to the order after release, including substitutions), the quantity required for manufacturing cost reporting is zero and reports show the quantity required as zero and the actual quantity picked as a variance.
The system captures the Qty required when you released the order. If the Qty complete differs from the Qty ordered (for example, you receive more or you close the order short), the system updates the Qty required.Quantity picked
Usage variance: Quantity picked - Original quantity required
Standard cost: Standard unit cost x Quantity required
If received and Qty complete exceeds Qty ordered: Standard unit cost x Quantity picked
If the original quantity required was zero (i.e., the component item was added or substituted) the standard cost shown is the standard unit cost multiplied by the quantity required when the item was added or substituted.Sub: s indicates the item was substituted for a different component (may be in whole or a partial substitution); * indicates this component was a substitution for another component. Example: A bill of material has these components: 1-1, 1-2 and 1-3. You substitute 1-D for 1-3 (i.e., 1.3 is not used): the report shows s for 1-3 and * for 1-D. If you then used some of 1-D and substituted yet another component, 1-D would be listed with *s (i.e., it was both a substitute and it was substituted with a different item).
Standard cost: Standard unit cost x Quantity required
If the Qty complete differs from the Qty ordered: Standard unit cost x Quantity picked
Avg to date: Quantity picked x Average unit cost
Act to date: Quantity picked x Actual unit cost
Std to date: Quantity picked x Standard unit cost
The setting for the Costing method for job cost option in the System Options Maintenance (XM) program (Manufacturing Options) for your manufacturing branch determines the unit cost
Price variance:
((Act to date / Qty picked) - (Standard cost / Qty required)) x Qty picked
((Avg to date / Qty picked) - (Standard cost / Qty required)) x Qty picked
((Std to date / Qty picked) - (Standard cost / Qty required)) x Qty pickedUsage variance: (Quantity picked - Quantity required) x (Standard unit cost / Quantity required)
Percent of standard:
Avg to date / Standard cost
Act to date / Standard cost
Std to date / Standard cost
Purchase Material Detail
If you selected the Include purchase material detail? Program option and you purchased non-stock or standard components for specific manufacturing orders, the register includes this information:
Item number purchased
Stocking unit of measure
Special purchase quantity
Quantity picked for this order
Special purchase cost:
For a non-stock item: PO unit cost x Quantity ordered
For an inventory item: Standard unit cost x Quantity ordered
Purchase order number
PO line number
Quantity ordered
Quantity received
PO unit cost
Actual extended purchase cost: PO unit cost x Quantity received or PO unit cost x Quantity picked based on the how the Allocate costs based on quantity picked system option (in System Options Maintenance - Manufacturing Options) is set.
Line status: C: Closed
Date due in stock
Outside Services Detail
If you selected the Include outside services detail? Program option and purchased labor for purchased service operations, the register includes this information:
Operation description
Order type: P/O: Purchase order
Order number
Order line number
Status: C: Closed
Stock due date
Operation sequence number
Quantity ordered
Quantity received to stock
Usage variance: Quantity received - Quantity ordered
Standard cost: Cost per piece x Quantity ordered
Actual cost: Invoiced cost x Quantity received
Price variance: Actual cost - Standard cost
Usage variance: (Quantity received - Quantity ordered) x Cost per piece
Percent of standard: (Actual cost / Standard cost) x 100
Total outside service cost: Total standard cost, actual cost, price variance, usage variance, and percent of standard
Labor/Labor Overhead Detail
If you selected the Include labor/labor overhead detail? Program option, the register includes this information for labor, labor overhead, and machine overhead.
Operation sequence number
Operation code
Work center
Good pieces
Department number
Operation type: B: Batch, R: Regular, U: Unattended
Machine number
Scrap pieces
Standard hours based on the routing at the time you released the order
Operation type |
Setups |
Standard hours calculation |
Regular |
1 |
(Hours per piece x Quantity ordered) + Setup time |
Regular |
Multiple |
Quantity ordered / Standard lot size = Number of setups rounded up to the next integer (Hours per piece x Quantity ordered) + (Number of setups x Setup time) |
Unattended |
1 |
Setup time |
Unattended |
Multiple |
Quantity ordered / Standard lot size = Number of setups rounded up to the next integer Number of setups x Setup time |
Batch |
|
Quantity ordered / Pieces per batch = Number of batches rounded up to the next integer (Number of batches x Hours per batch) + (Number of batches x Setup time) |
Standard dollars: (Standard hours x Direct labor rate) + (Setup time x Setup labor rate)
Actual hours:
If you entered pieces completed with the WIP Movement (WIPM) program:
Operation type |
Setups |
Actual hours calculation |
Regular |
1 |
(Good pieces x Hours per piece) + Setup time |
Regular |
Multiple |
Quantity ordered / Standard lot size = Number of setups rounded up to the next integer (Good pieces x Hours per piece) + (Number of setups x Setup time) |
Unattended |
1 |
Setup time |
Unattended |
Multiple |
Quantity ordered / Standard lot size = Number of setups rounded up to the next integer Number of setups x Setup time |
Batch |
|
((Hours per batch / Pieces per batch) x Good pieces) + Setup Setup = (Good pieces / Pieces per batch) rounded up to the next integer x Setup time |
If you entered reported hours with the Labor Entry (LLE) program or import them with the Labor Import (LEI) program for labor codes D (Direct), I (Indirect), O (Other), R (Rework), and U (Setup): Regular hours + Overtime hours
Actual dollars:
If you entered pieces completed with the WIP Movement (WIPM) program:
(Good pieces + Scrap pieces) x (Hours per piece or batch x Direct labor rate) + (Number of setups x Setup time x Setup labor rate)If you entered reported hours with the Labor Entry (LLE) program or imported them with the Labor Import (LEI) program:
(Regular hours + Overtime hours) x Direct labor rateEfficiency variance: Actual dollars - Standard dollars
Rate per use variance:
% of standard: (Actual cost / Standard cost) x 100
Total standard hours, standard dollars, actual hours, actual dollars, efficiency variance, rate per use variance, and % of standard
Operation sequence number
Operation code
Department number
Work center
Standard labor dollars:
For a regular or unattended operation with one setup:
(Hours per piece x Quantity ordered x Direct labor rate) + (Setup time x Setup labor rate)For a batch operation:
(Hours per batch x Quantity ordered x Direct labor rate) + ((Quantity ordered / Pieces per batch) x (Setup time x Setup labor rate))Actual labor dollars: ((Setup hours x Setup labor rate x Setup labor percent) / standard lot size) + (Hours per piece x Direct labor rate x Direct labor %)
Overhead rate code
Overhead percent
Standard overhead dollars: Labor x Overhead percentage
Actual overhead dollars: Labor x Overhead percentage + Labor overhead adjustments
Overhead efficiency: Actual overhead dollars - Standard overhead dollars
Overhead rate per use variance: % of standard: (Actual cost / Standard cost) x 100
Total standard dollars, actual dollars, overhead efficiency variance, overhead rate per use variance, and % of standard
Operation sequence
Operation code
Work center
Good pieces
Department
Operation type: U: Unattended
Machine number
Scrap pieces
Standard hours: (Hours per piece x Quantity ordered)
Standard dollars: (Standard hours x Machine labor rate) + (Standard hours x Machine labor rate x Total overhead rate for work center x .01)
Actual hours: (Hours per piece x Good pieces)
Actual dollars: (Actual hours x Machine labor rate) + (Actual hours x Machine labor rate x Overhead percent x .01)
Efficiency variance: Machine overhead - Burden applied
Rate per use variance: % of standard: (Actual dollars / Standard dollars) x 100
Total standard hours, standard dollars, actual hours, actual dollars, efficiency variance, rate per use variance, and % of standard
Adjustment Detail
If you selected the Include adjustment detail? Program option and entered cost adjustments, the register includes this information:
Adjustment type
Adjustment sequence number
Adjust amount
Authority entered in the Manufacturing Cost Adjustments (MCA) program
Transaction date on which the adjustment was entered
Adjustment code
Adjustment code description
Total adjustment amount
Scrap
If you selected the Include component scrap detail? Program option and entered component scrap in the WIP Movement (WIPM) program or Labor Entry (LLE) program, or imported with the Labor Import (LEI) program, the report includes this information:
Component: component item number
Rtg seq: routing sequence where the component scrap occurred
Employee number: employee who reported the scrap
Quantity: how many of this component were scrapped
Value: quantity scrapped for this component x the component's standard cost
Job Cost Summary
If you selected the Include job cost summary? Program option, the register includes this information:
The system captured the Qty required when you released the order. If the Qty complete differs from the Qty ordered, the system updates the Qty required.
Field |
Standard |
Cost to date |
Variance |
% std |
Material |
SUM (Qty of components required for the quantity completed x Standard unit cost) |
(Qty picked x Actual, average, or standard unit cost) + Material stock adjustments + Special purchase adjustments |
Actual, average, or standard - Standard |
(Actual, average, or standard / Standard) x 100 |
Outside srv |
Cost per piece x Quantity required |
(Invoiced cost x Quantity received) + Outside service adjustments |
Actual - Standard |
(Actual / Standard) x 100 |
Labor |
((Setup hours x Setup labor rate x Setup labor percent) / standard lot size) + (Hours per piece x Direct labor rate x Direct labor %) (Number of batches x Hours per batch) + (Number of batches x Setup time) |
Total labor cost for completed operations + Labor adjustments If you entered pieces completed: (Good pieces + Scrap pieces) x (Hours per piece or batch x Direct labor rate) + (Number of setups x Setup time x Setup labor rate) If you entered or imported reported hours: (Regular hours + Overtime hours) x Direct labor rate |
Actual - Standard |
(Actual / Standard) x 100 |
Labor ovhd |
Labor x Overhead percentage |
(Good pieces + Scrap pieces) x ((Hours per piece or batch x Direct labor rate) + Setup cost) x (Total overhead rate for work center x .01) + Labor overhead adjustments If you enter actual hours with the Labor Entry (LLE) program or import them with the Labor Import (LEI) program: (Reported hours x Direct labor rate) x (Total overhead rate for work center x .01) |
Actual - Standard |
(Actual / Standard) x 100 |
Machine ovhd For an unattended operation |
(Setup hours x Machine rate) / Standard lot size) + Hours per piece x Machine rate) + ((Setup hours x Machine rate) / Standard lot size) + (Hours per piece x Machine rate) x Overhead percentage) |
(Setup hours x Machine rate) / Standard lot size) + Hours per piece x Machine rate) + ((Setup hours x Machine rate) / Standard lot size) + (Hours per piece x Machine rate) x Overhead percentage) + Machine overhead adjustments |
Machine overhead - Burden applied |
(Actual / Standard) x 100 |
Adjustments |
|
Miscellaneous adjustments (type X) |
Actual adjustments |
|
Totals |
Material + Outside services + Labor + Labor overhead + Machine overhead |
Material + Outside services + Labor + Labor overhead + Machine overhead + Miscellaneous adjustments |
Cost to date - Standard |
(Actual / Standard) x 100 |
History
When you enter PROCEED for the If the register is correct, enter PROCEED to update prompt, the program moves closed manufacturing orders to history. Some reports and inquiries have an Include history? Program option. If you select this option, These programs have the option:
Manufacturing Order Listing (MHL)
Manufacturing Order Cost Detail Report (MJCP)
Manufacturing Order Status Summary (MJR)
Manufacturing Order Cost Report (MJS)
Manufacturing Order Analysis Inquiry (MOA)
Manufacturing Order Summary Inquiry (MOAQ)
Manufacturing Period Activity (MPA)
WIP Valuation Report (WIV)
Audit Trail
To activate an audit trail, select one of the files listed below in the Audit Trail Maintenance (XAT) program. The system records all transactions. You can then run the Audit Trails (ATR) program and select that file to print a report of these transactions.
MP2: Mfg Order Master
MP9: Mfg Order Components
O1S: Shipment Header
O1SB: Shipment Addresses
O1SF: Shipment Freight Detail
O1SL: Shipment Lines
VR1: Receiver Header
VR1B: Receiver Lines
VR1BD: Receiver Line Detail
WIPF: Work-in-process Header
WIPFD: Work-in-process Detail