Display WIP Costs
Use the WIP Cost Inquiry (WICQ) program to display work in process labor, overhead, setup, outside service, and other costs for a manufacturing order. See Road Map for work flow.
Enter the number of the manufacturing order or click Lookup and use the standard lookup options to select the order from a list.
The program displays information about the manufacturing order:
Field Name |
Displays |
||||||||||||||||
Mfg order no |
The manufacturing order number that you entered or selected followed by its status:
|
||||||||||||||||
Parent item no |
The parent item number ordered on this manufacturing order |
||||||||||||||||
Description |
The description of the parent item |
||||||||||||||||
ECL |
The Engineering Change Level for this manufacturing order |
||||||||||||||||
RRL |
The Routing Revision Level for this manufacturing order |
||||||||||||||||
Qty ordered |
The quantity of this parent item to be manufactured for this order |
||||||||||||||||
Qty scrapped |
The quantity of the parent item scrapped |
||||||||||||||||
Qty received |
The quantity received into inventory |
||||||||||||||||
Qty rejected |
The quantity of this item rejected during inspection |
||||||||||||||||
Qty stocked |
The quantity received into inventory in the stocking unit of measure; this quantity can differ from the Qty received if some are awaiting inspection |
||||||||||||||||
Released |
The date the manufacturing order was created |
||||||||||||||||
Due |
The date this order is due |
||||||||||||||||
Picked |
The date components were picked |
||||||||||||||||
Completed |
The date this order was completed |
The program displays these fields for each operation:
Field Name |
Displays |
Oper seq |
The operation sequence number |
Accum lbr cost |
The total labor cost to date for this operation For a regular operation: Hours per piece x Good pieces x Direct labor rate For a batch operation: (Hours per batch / Pieces per batch) x Good pieces x Direct labor rate |
Accum lbr OH |
The total labor overhead cost: Labor cost x Total overhead rate for work center x .01 |
Accum mach OH |
For an unattended operation: (Hours per piece x Machine labor rate x Good pieces) + (Hours per piece x Machine labor rate x Good pieces x Total overhead rate for work center x .01) |
Accum setup cost |
The setup cost per operation: Setup time x Setup labor rate For a regular or unattended operation: (Good pieces / Standard lot size) x (Setup time x Setup labor rate) For a batch operation: (Good pieces / Pieces per batch) x (Setup time x Setup labor rate) |
Accum oth cost |
The labor hours entered in the Labor Entry Maintenance (LLE) program or imported with the Labor Import (LEI) program for the Labor code O (Other) |
Accum OS serv |
The total outside service cost for this operation |
Accum rwrk cost |
The labor hours spent repairing pieces for this order |
Oper type |
Operation type: |
Work center |
The work center at which this operation occurs |
Good |
The quantity of usable pieces completed |
ST |
The operation sequence type: Standard or Alternate |
Mach no |
The machine number for the work center |
Accum scrap pieces |
The quantity scrapped |
% Comp |
The percent of this operation that has been completed |
Oper cd |
The operation code |
Remaining |
The quantity not yet completed |
(Optional) Highlight a line and click Routing to display hours per piece, setup time, setup and direct labor codes, and other information. The information that displays depends on the operation type:
If operation type |
See |
R for Regular or B for Batch |
|
P for Purchased service |
|
I for Indirect |
|
U for Unattended |
Click OK to return to this program.
Choose the appropriate options:
To |
Do This |
Print WIP costs |
Click Print. See Print an Inquiry. |
Display only total labor, labor overhead, machine overhead, setup, other, outside service, and rework costs |
Click Totals. Click Totals again to return to the operation list. |
Display components for this manufacturing order |
Click Component. See Display Component Requirements. Click OK to return to this program. |
Display hours per piece, setup time, setup and direct labor codes for an operation |
Highlight a line and click Routing. See step 2. |
Display labor detail for this manufacturing order |
Click Labor. See Display Labor for a Manufacturing Order. |
Specify a different manufacturing order |
Click OK. See step 1. |
Exit the program |
Click Exit. |