Enter Standard ECO Costs

When you click Costs and then click ECO costs in the ECO Maintenance (ECO) program you can enter and change standard ECO costs. See Background and Road Map for more information.

The program lists ECO cost descriptions.

Note

Only rates set up in the ECO Rate Codes (TECORT) program calculate totals.

  1. Enter data in these fields:

Field Name

Type / Max Length

Action / Description

Rate

Optional
14 numeric in the format 999999999.99999

For an hourly rate, enter the amount per hour.
For a quantity cost, enter the amount for each.

Hours

Optional
7 numeric in the format 99999.99

Enter the number of hours and minutes to complete the task.

Quantity

Optional
11 numeric

Enter the quantity of each.

  1. Click Apply. The program calculates the extended cost and the total standard ECO costs.

  1. Choose the appropriate options:

To

Do This

Accept the data

Click OK.

Exit without creating standard ECO costs

Click Cancel.

Calculate extended costs and totals

Click Apply.

Enter notes for standard costs

Click Notes. See Enter Notes.

This button is inactive for processed ECOs.

Clear hours and quantities and set totals to .00 (zero).

Click Clear fields.

  1. Choose the appropriate options when you click OK or Cancel:

To

Do This

Change a field

Click Modify. See Change an Engineering Change Order.

Exit without creating this change order

Click Cancel.

Enter notes and enter the reason for creating the change order

Click Notes. Click Reason for change and enter the reason for the change order. See Enter Notes.

Enter or change data in custom fields your company uses

Click User. See Enter Data in User and Shadow File Fields.

This button displays only if you have set up user fields for this program in the User Fields Maintenance (XMO) program.

Close this engineering change order

Click Close ECO. See Close an Engineering Change Order.

Select the compliance, effectivity, and type of change codes for this change order

Click ECO impact and then:

Click

To

Compliance

Select compliance codes. See Select ECO Compliance Codes.

Effectivity

Select effectivity codes. See Select ECO Effectivity Codes.

Type of chg

Select the type of change codes. See Select ECO Type of Change.

Back

End this action.

Select the required signoffs for this change order

Click Sign off. See Select ECO Signoffs.

Select the required implementation signoffs for this change order

Click Implement. See Select ECO Implementation Signoffs.

Maintain ECO costs, view the cost summary, and calculate costs

Click Costs and then:

Click

To

ECO costs

Enter standard change order costs. See Enter Standard ECO Costs.

Misc costs

Enter miscellaneous change order costs and descriptions. See Enter Miscellaneous Costs.

Cost roll up

Calculate ECO cost totals.

Cost summary

View old and new materials costs See Enter Engineering Change Order Items.

Back

End this action.

Select the item numbers required for the change order

Click ECO items.
See Enter Engineering Change Order Items.

Send out notifications for approval signoff

Click Appvl/Signoff. See Background for more information.

Send out notifications for implementation approval signoff

Click Appvl/Implement. See Background for more information.

Print the engineering change order

Click Print ECO. See Print or Reprint Documents.

Accept the data and exit this order

Click OK.

  1. Choose the appropriate options when you click OK or Cancel:

To

Do This

Display the selected record

Click OK.

Display the previous record in the file

Click Prev.

Display the next record in the file

Click Next.

Enter a new change order

Click New.

Exit the program

Click Exit.