Calculate Material Requirements
Use the Material Requirements Planning (MRP) program to calculate time-phased requirements for raw material and components, plan the timely replenishment of inventory, and reschedule or cancel existing non-firm orders. See Background and Road Map for more information.
Set your options:
Click the Runtime tab to set runtime options. See Set Options for Reports and Inquiries for more information.
Click the Selection tab to select items by buyer, planner, product class, or item code.
Click the Program tab to set these program specific options:
Field Name |
Type / Max Length |
Action / Description |
||||||||||
Select horizon date |
Required |
Select the date on the shop calendar from which you want the program to begin each item's plan or enter a date shortcut. The program includes planned orders with a start date that is on or before the terminal date. |
||||||||||
Select report type |
Required |
Select the type of report you want to print:
Your choice of report type does not affect the plan; it determines the data the program prints on the report after the plan is complete. System options (at both enterprise and manufacturing branch levels) include filters to limit exception messages. See Set Manufacturing Options. |
||||||||||
Select sort option |
Required |
Select how you want the report sorted:
|
||||||||||
Pegging? |
Optional |
Select if you want to print a Requirements pegging report for each item or leave blank if you do not. |
||||||||||
Select latest date to peg |
Optional |
If you selected Pegging?, select the cutoff date for pegging detail or enter a date shortcut. You can use any future date or leave blank to peg all dates. The Requirements pegging report will include demand orders with due dates on or before this date. |
||||||||||
Select cushion days |
Required |
Enter the number of days the current
plan should be held firm. |
||||||||||
Excess exceptions? |
Optional |
Select if you want the report to include exceptions when you have an overabundance of orders for a specific period or leave blank if you do not. |
||||||||||
Print exceptions for future periods? |
Optional |
Select to print exceptions for future periods on the report or leave blank to exclude them. |
||||||||||
Select exception report type |
Required |
Select the type of runtime exception report you want:
The long report potentially provides a more detailed explanation of the runtime exceptions than the short report; however, there may be no difference between the reports. |
||||||||||
Print new page for each item? |
Optional |
Select to print each planned item on a new page or leave blank to print a continuous report. |
||||||||||
Erase work files? |
Optional |
Select to erase work files after printing or leave blank if you want to save the work files for subsequent report printing. If you leave this option blank and selected F for Select report type, you can subsequently select either I or E for Select report type and click Reprint. You can also select a different factor for Select sort option (B for buyer code, P for planner code, or C for product class). In addition, you can also change your Selection options. You should leave this field blank if you have vendor contracts. The program requires work files to create requisitions for each contract. |
||||||||||
Select planning display period code |
Optional |
Select a code to override the item-specific planning display codes. The program plans items based on the code selected for the Planning period field in the item's record in the Branch Item Maintenance (IMB) program. If that field is blank, the program uses the DFAULT planning display code. |
||||||||||
Output device |
Optional |
Select the device to which you want to output the report or leave blank to use your default output device. |
||||||||||
Regenerative? |
Optional |
When selected, all MRP items are processed. Selecting Regenerative? is as if the MRP Action File Maintenance (MAF) program were first run to populate the planning action file with all items. Leave blank for a "net change" report. |
Choose the appropriate options:
To |
Do This |
Process the report |
Click Process. See Background for a list of what prints.
When you click Reprint, the program uses the report type, sort option, and selection options you selected. Therefore, the ** Reprint ** report may be different from your original report.
|
Save these options for future use |
Click Save. |
Exit the program |
Click Exit. |