Enter Good and Scrap Quantities

When you click Movement in WIP Movement (WIPM) or Work Center Operations (WCO), you can report good parent items and report scrapped parent items and components.

The program displays information about the order and selected routing operation:

Field Name

Displays

Mfg branch

The manufacturing branch

Mfg order no

The manufacturing order number

Operation seq no

The operation sequence number

Sequence number

The system-assigned sequence number for the transaction

Parent item no

The parent item number

Description

The description of the parent item

Work center no

The work center number where this operation is performed

Machine no

The machine number at this work center

Operation cd

The operation code for this operation

Qty ordered

The quantity ordered

Accum good pcs

The quantity of good pieces produced for this operation before you entered Good pieces

Accum scrap pcs

The quantity of scrapped pieces for this operation before you entered Scrap pieces

Remaining pcs

The quantity of units remaining for this operation before you entered Good pieces or Scrap pieces

  1. Choose the appropriate options:

To

Do This

Enter good and scrapped parent quantities

See step 2.

Scrap components

Click Comp scrap. See Scrap or Reject Components.

Return to previous screen

Click OK.

Specify a different manufacturing order

Click Quit. See WIP Movement.

  1. Enter data in these fields:

Field Name

Type / Max Length

Action / Description

Good pieces

Optional
11 numeric

Enter the quantity of usable pieces produced.

You can enter a negative quantity to correct a previous entry. However, if you enter a negative quantity and your manufacturing option Backflush components by operation seq? is active, the system does not return previously backflushed components to inventory. A message advises that component picking adjustments may be required.

Scrap pieces

Optional
11 numeric

If the parent item and all its components need to be scrapped, enter the quantity of unusable parent items to be scrapped.

To scrap components, leave this field blank. Click Comp scrap. See Scrap or Reject Components.

Trans date

Required
10 date

Accept the displayed transaction date, select another date, or enter a date shortcut.

Employee no

Optional
10 alphanumeric

Enter the number of the employee who performed this work or click the Lookup icon and use the standard lookup options to select the employee from a list.

% complete

Conditional
5 numeric in the format 999.99

Leave blank to have the program calculate the percent complete based this formula: ((Accum good + Accum scrap) / Qty ordered) x 100 or you can enter a percent greater than the calculated percent. For long running operations you may want to enter a larger percentage when the quantity has yet to be completed.

To close out the operation with remaining pieces greater than zero, enter 100.00.

If you selected the Select ctrl no for oper seq backflush? option in the System Options Maintenance (XM) program (Manufacturing Options) and a component is lot or serial controlled, the program displays the number or numbers selected.