Partially Receive a Purchase Order
When you leave the Receive complete? field blank in the Receiver Maintenance (IRC), you can receive selected lines or a quantity that is different from the quantity open on the purchase order line.
The program displays the PO number and vendor, followed by these fields for each purchase order line:
Field Name |
Displays |
Ln |
The purchase order line number |
Sel |
Selected:
This PO line is selected to be received |
Insp? |
Selected:
This PO line requires inspection |
Item no |
The item number on the line |
Description |
The item description |
Pur UOM |
The purchasing unit of measure |
Pur qty ord |
The quantity ordered in the purchasing unit of measure |
Pur qty rcvd |
The quantity that will be received when you click OK |
Qty to receive |
The quantity to be received in the purchasing unit of measure |
Rcv cert? |
Whether this item requires a certificate of compliance (determined by the setting of the Receiving cert reqd field in Enterprise Item Maintenance):
|
M/L |
Indicates with the PO line is for material or labor (i.e., a purchased service) |
Demand order |
The source of the demand for this PO line |
Stk UOM |
The unit of measure you stock the item in |
Due in stock |
The date the item is due in stock from the PO line (i.e., the date promised plus the item's put-away lead time) |
Choose the appropriate option:
To |
Do This |
Review your options for this program |
Click Prog opts. This button is available only if you can set options for this program. |
Select/de-select a PO line |
Highlight a line and click Select or double click the line. A check mark in the Sel column indicates the line is selected for receipt. Click Select again to de-select the line; the quantity to receive is cleared. Note If this item requires a certificate of compliance, the program
prompts appropriately. When you select a line, the Qty to receive defaults to the open quantity. See Modify to receive a different quantity. |
Go a related program |
Highlight a line and click Jump. See Jump. |
Display the purchase order |
Highlight a line and click Order. See Display a Summarized Purchase Order. Click OK to return to this program. |
Change the quantity to receive or close a PO line |
Highlight a line and click Modify. The program prompts Enter qty to receive. Enter or change the quantity as required. You may also be prompted to close the PO line (i.e., if the Allow PO line close during receipt? system option is selected). Click OK if your entries are correct or click Cancel to leave the line unchanged. If this item requires a certificate of compliance, the program
prompts appropriately. The program displays a message if you attempt to receive more than the open quantity. The item's receipt tolerance (maintained in Branch Item Maintenance) determines the action that is taken. See Receipt Tolerance Codes Maintenance for a discussion of possible actions. |
Select/de-select all lines |
Highlight a line and click All. If any item requires a certificate of compliance when you select all lines, the program prompts appropriately. Note |
Receive selected lines (the Qty to receive column displays the quantity you are receiving) |
Click OK. The program assigns a receiver number. Received items that do not require inspection are either stocked or staged to be put away by Receiving and Inspection based on the receiving method selected for your system. If any of the items received are stocked in multiple locations or have control numbers (specified in Enterprise Item Maintenance), you are prompted to enter stocking location and/or lot/serial numbers as required. See Enter Control Information. |