Add or Change Manufacturing Order Components
When you click Component in Material Usage Maintenance (MUA), Manufacturing Order Maintenance (MIM), Picking Confirmation (MPK) or Work Center Operations (WCO), the manufacturing order summarized at the top of the display and components are listed:
Field Name |
Displays |
||||||||||
Comp item no |
The number of a component |
||||||||||
Part des |
The identifier your company uses to distinguish multiple occurrences of a component in the same bill of material |
||||||||||
Sts |
C indicates the component is closed |
||||||||||
Qty required |
The quantity of this component required to complete this manufacturing order: Current qty per x Quantity ordered + (Current qty per x Quantity ordered x Curr scrap % x .01) rounded to up the next integer |
||||||||||
Net required |
The quantity
required is the quantity of the component required to complete
this manufacturing order: |
||||||||||
Qty obligated |
The quantity of this component that has been obligated |
||||||||||
Qty picked |
The quantity of this component that has been picked |
||||||||||
Qty in picking |
The of this component that is in picking |
||||||||||
Comp due |
The date this component is required |
||||||||||
FS code |
The component's floor stock code |
||||||||||
Op seq |
The operation sequence at which the system picks this component, if you selected the Backflush components by operation seq? option for your manufacturing branch in the System Options Maintenance (XM) program (Manufacturing Options) and entered a sequence for this component in the Bill of Material Maintenance (MPS) program |
||||||||||
Sub type |
One of the following:
|
||||||||||
Substituted |
Y indicates the item was substituted for another component |
||||||||||
Item description |
The description of the component |
||||||||||
Seq |
A sequence number the program assigned to this component |
||||||||||
Stk UOM |
The component's stocking unit of measure |
||||||||||
Spec |
A check mark indicates this is a special purchase item |
||||||||||
Spec qty ord |
How many of the special purchase item were ordered |
||||||||||
Curr scr % |
The scrap percentage |
Choose the appropriate options:
To |
To This |
Add a component to this manufacturing order |
Click Add. See step 2. |
Change a component quantity, due date or other information |
Highlight the line and click Select or double click the line. See step 3. |
Review your options for this program |
Click Prog opts. See Set Material Usage Maintenance Options. |
Obligate a component |
Highlight the line and click Obligate. |
Pick the obligated components |
Click Pick. See Pick Selected Components. |
Close short all open components |
Click Close short. See Close All Open Components. |
Print or reprint shop paper for this manufacturing order |
Click Shop paper. See Print or Reprint Documents. |
Re-open a closed component |
Highlight the line and click Re-open comp. |
Return to the previous program |
Click OK. The program exits to the program you were in when you clicked Component |
Enter data in these fields:
Field Name |
Type / Max Length |
Action / Description |
Comp item no |
Required |
Enter the item number of a component or click the Lookup icon and use the standard lookup options to select the item from a list. If this is a rework order, the component can be the same as the parent item. |
Part designator |
Optional |
Enter the identifier your company uses if this component is to be listed on this bill of material more than once. You may call this designator a balloon number, bubble number, file number, material tag, or reference number. |
Unique seq |
Display only |
A sequence number the program assigned to this component |
The component's description are stocking unit of measure are displayed. Enter data or change data in these fields:
Field Name |
Type / Max Length |
Action / Description |
Current qty per |
Conditional |
Enter a greater than zero quantity of the component required to build one parent item. Click Qty req if you want to enter the quantity required for the order instead of the quantity per. |
Curr scrap % |
Optional |
Enter the percent of this component that you usually scrap during the manufacturing process. The program adjusts the Qty required field on the right: Current qty per x Quantity ordered + (Current qty per x Quantity ordered x Curr scrap % x .1) rounded to up the next integer You can change this field anytime before you obligate this component. |
Flr stk cd |
Display only |
The item's floor stock code (assigned in Branch Item Maintenance) |
Component due date |
Optional |
Accept the displayed due date, select another date, or enter a date shortcut. When you add a new component, the component due date is set to the manufacturing order start date. |
Special purchase |
Display only |
A check mark indicates this component was purchased specifically for this manufacturing order |
Status |
Display only |
The status of this
component: |
Pick per receipt? |
Display only |
A check mark indicates that backflushed components are rounded based on each receipt quantity. See Overview: Component Backflushing. |
Operation seq no |
Conditional |
If you selected
the Backflush components by operation seq? option for your
manufacturing branch in the System Options Maintenance (XM) program
(Manufacturing Options), enter the operation sequence at which
you want the system to pick this component. |
Comp reference |
Optional |
Enter the reference your company uses. Note |
Picking warehouse |
Optional |
Select or enter the warehouse from which the item is backflushed |
Picking bin location |
Optional |
Enter the bin location from which the component is backflushed or use the lookup to select one from which the item is backflushed |
Qty per at release |
Display only |
The quantity of the component required to build one parent item when the order was released |
Scrap % |
Display only |
The percent of this component that you usually scrap during the manufacturing process. This percent comes from the bill of material and defaults into the Curr scrap % field. The program uses this scrap factor to calculate the initial quantity required for the component. |
Qty required |
Conditional |
The quantity of the item required to build the quantity ordered of the parent: Current qty per x Quantity ordered + (Current qty per x Quantity ordered x Curr scrap % x .1) rounded up to the next integer Click Qty per if you want to specify the quantity required for the order instead of the quantity per. |
Outside supply |
Display only |
The quantity that has been ordered on a requisition, PO, transfer, or manufacturing order |
Supply released |
Display only |
The quantity on a requisition that has been released (converted to a PO, transfer, or manufacturing order) or the quantity that has been released to the shop floor |
Qty obligated |
Display only |
The quantity of this component that has been obligated |
Qty in picking |
Display only |
The quantity of this component that is waiting to be picked |
Qty picked |
Display only |
The quantity of this component that has been picked |
Qty scrapped |
Display only |
The quantity of this component that was scrapped during manufacturing |
Qty rejected |
Display only |
The quantity of this component that was rejected during manufacturing |
Choose the appropriate options:
To |
To This |
Change a field |
Move the cursor to the field, make changes and click Apply.to accept the change or click Cancel to abandon the change. |
Enter notes for this component |
Click Notes. See Enter Notes. |
Go to a related program |
Click Jump. See Jump. |
Display the changes made to the order |
Click Audit.
See Display an Audit Trail.
Click OK after you view
the audit trail to return to this program. |
Obligate this component |
Click Obligate. See Obligate Items. This button is not available if this is a floor stock component. |
Display control numbers and/or warehouse/bin locations for picked components |
Click Ctrl info. See Display Control Information for Picked Components. Click OK to return to this program. |
Change the quantity required for the order |
Click Qty req and enter the quantity needed in the Qty required field. Click Apply to accept or click Cancel to reject your entry. When you click Apply, the Current qty per field is calculated based on your entry. Click Qty per if you want to change the Current qty per and let the system calculate the Qty required. |
Close the component short |
Click Close short. This button is available if you can close this component short. |
Re-open a closed component |
Click Re-open comp. This button is available if the component is closed. |
Display substitutes for the component |
Click View subs. This button is available only if substitutes have been set up for the item. |
Substitute this item with another item |
Click Substitute. See Substitute Components. |
Accept the data |
Click OK. If you selected Automatic for the Select obligation mode Program option, the program prompts Comp item no, Part designator, and Unique Seq. Enter another component or leave blank to exit. If you selected Manual for the Select obligation mode Program option, the program displays the obligation selector. See Obligate Items. The program returns to the component list. See step 1. |