Add or Change Manufacturing Order Components

When you click Component in Material Usage Maintenance (MUA), Manufacturing Order Maintenance (MIM), Picking Confirmation (MPK) or Work Center Operations (WCO), the manufacturing order summarized at the top of the display and components are listed:

Field Name

Displays

Comp item no

The number of a component

Part des

The identifier your company uses to distinguish multiple occurrences of a component in the same bill of material

Sts

C indicates the component is closed

Qty required

The quantity of this component required to complete this manufacturing order: Current qty per x Quantity ordered + (Current qty per x Quantity ordered x Curr scrap % x .01) rounded to up the next integer

Net required

The quantity required is the quantity of the component required to complete this manufacturing order:
Current qty per x Quantity ordered + (Current qty per x Quantity ordered x Curr
scrap % x .1)
rounded up to the next integer.
Net required is the quantity required to be picked, adjusted for components that were substituted, closed short or overpicked.  It is calculated as the quantity required (as described above) + quantity overpicked - quantity closed short.

Qty obligated

The quantity of this component that has been obligated

Qty picked

The quantity of this component that has been picked

Qty in picking

The of this component that is in picking

Comp due

The date this component is required

FS code

The component's floor stock code

Op seq

The operation sequence at which the system picks this component, if you selected the Backflush components by operation seq? option for your manufacturing branch in the System Options Maintenance (XM) program (Manufacturing Options) and entered a sequence for this component in the Bill of Material Maintenance (MPS) program

Sub type

One of the following:

Blank

No substitute item is set up for the component

I

Substitute component exists for the item master

C

Substitute component exists on the bill of material component

B

Substitute component exists for both the item master and the bill of material component

N

No substitutes allowed for this component—the Subs prohibited? check box is selected in the Bill of Material Maintenance (MPS) program.

Substituted

Y indicates the item was substituted for another component

Item description

The description of the component

Seq

A sequence number the program assigned to this component

Stk UOM

The component's stocking unit of measure

Spec

A check mark indicates this is a special purchase item

Spec qty ord

How many of the special purchase item were ordered

Curr scr %

The scrap percentage  

  1. Choose the appropriate options:

To

To This

Add a component to this manufacturing order

Click Add. See step 2.

Change a component quantity, due date or other information

Highlight the line and click Select or double click the line. See step 3.

Review your options for this program

Click Prog opts. See Set Material Usage Maintenance Options.

Obligate a component

Highlight the line and click Obligate.

Pick the obligated components

Click Pick. See Pick Selected Components.

Close short all open components

Click Close short. See Close All Open Components.

Print or reprint shop paper for this manufacturing order

Click Shop paper. See Print or Reprint Documents.

Re-open a closed component

Highlight the line and click Re-open comp.

Return to the previous program

Click OK. The program exits to the program you were in when you clicked Component

  1. Enter data in these fields:

Field Name

Type / Max Length

Action / Description

Comp item no

Required
24 alphanumeric

Enter the item number of a component or click the Lookup icon and use the standard lookup options to select the item from a list.

If this is a rework order, the component can be the same as the parent item.

Part designator

Optional
8 alphanumeric

Enter the identifier your company uses if this component is to be listed on this bill of material more than once. You may call this designator a balloon number, bubble number, file number, material tag, or reference number.

Unique seq

Display only

A sequence number the program assigned to this component

  1. The component's description are stocking unit of measure are displayed. Enter data or change data in these fields:

Field Name

Type / Max Length

Action / Description

Current qty per

Conditional
12 numeric in the format 9999999.99999

Enter a greater than zero quantity of the component required to build one parent item.

Click Qty req if you want to enter the quantity required for the order instead of the quantity per.

Curr scrap %

Optional
5 numeric in the format 999.99

Enter the percent of this component that you usually scrap during the manufacturing process.

The program adjusts the Qty required field on the right: Current qty per x Quantity ordered + (Current qty per x Quantity ordered x Curr scrap % x .1) rounded to up the next integer

You can change this field anytime before you obligate this component.

A scrap percentage can be set for components in the Bill of Material Maintenance (MPS) program.

Flr stk cd

Display only

The item's floor stock code (assigned in Branch Item Maintenance)

Component due date

Optional
10 date

Accept the displayed due date, select another date, or enter a date shortcut.

When you add a new component, the component due date is set to the manufacturing order start date.

Special purchase

Display only

A check mark indicates this component was purchased specifically for this manufacturing order

Status

Display only

The status of this component:
Blank
: Open
C
: Closed, no open requirements

Pick per receipt?

Display only

A check mark indicates that backflushed components are rounded based on each receipt quantity. See Overview: Component Backflushing.

Operation seq no

Conditional
4 alphanumeric

If you selected the Backflush components by operation seq? option for your manufacturing branch in the System Options Maintenance (XM) program (Manufacturing Options), enter the operation sequence at which you want the system to pick this component.

If you also selected the Backflush comps not attached to oper? option, leave blank to pick this component when you enter pieces completed for the first sequence in the WIP Movement (WIPM) program.

If this component is not required until the third operation sequence, enter that sequence number. When you enter work-in-process for the third sequence or for a subsequent sequence, the system backflushes picking of this component.

Comp reference

Optional
30 alphanumeric

Enter the reference your company uses.

Note
This field may have a different label based on the Component reference user label option in System Options Maintenance (XM) program (Manufacturing Options).

Picking warehouse

Optional
2 alphanumeric

Select or enter the warehouse from which the item is backflushed

Picking bin location

Optional
8 alphanumeric

Enter the bin location from which the component is backflushed or use the lookup to select one from which the item is backflushed

Qty per at release

Display only

The quantity of the component required to build one parent item when the order was released

Scrap %

Display only

The percent of this component that you usually scrap during the manufacturing process. This percent comes from the bill of material and defaults into the Curr scrap % field. The program uses this scrap factor to calculate the initial quantity required for the component.

Qty required

Conditional
10 numeric in the format 9999999999

The quantity of the item required to build the quantity ordered of the parent: Current qty per x Quantity ordered + (Current qty per x Quantity ordered x Curr scrap % x .1) rounded up to the next integer

Click Qty per if you want to specify the quantity required for the order instead of the quantity per.

Outside supply

Display only

The quantity that has been ordered on a requisition, PO, transfer, or manufacturing order

Supply released

Display only

The quantity on a requisition that has been released (converted to a PO, transfer, or manufacturing order) or the quantity that has been released to the shop floor

Qty obligated

Display only

The quantity of this component that has been obligated

Qty in picking

Display only

The quantity of this component that is waiting to be picked

Qty picked

Display only

The quantity of this component that has been picked

Qty scrapped

Display only

The quantity of this component that was scrapped during manufacturing

Qty rejected

Display only

The quantity of this component that was rejected during manufacturing

  1. Choose the appropriate options:

To

To This

Change a field

Move the cursor to the field, make changes and click Apply.to accept the change or click Cancel to abandon the change.

Enter notes for this component

Click Notes. See Enter Notes.

Go to a related program

Click Jump. See Jump.

Display the changes made to the order

Click Audit. See Display an Audit Trail. Click OK after you view the audit trail to return to this program.

Note

Audit trail logging must be activated.

Obligate this component

Click Obligate. See Obligate Items.

This button is not available if this is a floor stock component.

Display control numbers and/or warehouse/bin locations for picked components

Click Ctrl info. See Display Control Information for Picked Components. Click OK to return to this program.

Change the quantity required for the order

Click Qty req and enter the quantity needed in the Qty required field. Click Apply to accept or click Cancel to reject your entry. When you click Apply, the Current qty per field is calculated based on your entry.

Click Qty per if you want to change the Current qty per and let the system calculate the Qty required.

Close the component short

Click Close short.

This button is available if you can close this component short.

Re-open a closed component

Click Re-open comp.

This button is available if  the component is closed.

Display substitutes for the component

Click View subs.

This button is available only if substitutes have been set up for the item.

Substitute this item with another item

Click Substitute. See Substitute Components.

Accept the data

Click OK.

If you selected Automatic for the Select obligation mode Program option, the program prompts Comp item no, Part designator, and Unique Seq. Enter another component or leave blank to exit.

If you selected Manual for the Select obligation mode Program option, the program displays the obligation selector. See Obligate Items.

The program returns to the component list. See step 1.