Enter a Bill of Material
Use the Bill of Material Maintenance (MPS) program to enter or change, copy, and delete a bill of material for standard and phantom items. See Background and Road Map for more information.
Enter the number of the parent item or click the Lookup icon and use the standard lookup options to select the parent item number from a list. The lookup displays bills of material that are currently on file. To switch to a lookup by item number, click the By item button in the lookup display.
The description of the selected parent item number, item type description, stocking unit of measure, item status, current ECL, make/buy/kit and bypass code are displayed.
Existing ECLs are listed:
Field Name |
Displays |
ECL |
The engineering change level |
Curr |
* (asterisk) indicates the current ECL |
Eng drawing no |
The engineering drawing number |
Date entered |
The date the bill was entered |
Type |
The item type code based on the component's order and bypass codes; see Item Types |
Approval status |
Whether or not the bill is approved |
Date/time stamp |
The last date and time the bill was changed |
Choose the appropriate options:
| To | Do This |
| Add an ECL | Click Add. Enter the ECL (up to 4 characters) you want to create and click OK. See step 3. |
| Delete an ECL | Highlight the ECL you want to delete and click Delete. See Delete. |
Change an ECL |
Highlight the ECL you want to change and click Select or double click the line. See step 3. |
Print the list of ECLs |
Click Print. See Print. |
Copy an ECL |
Highlight the ECL you want to copy and click Bill copy. See Copy a Bill of Material. |
Specify a different parent item |
Click OK. See step 1. |
Exit the program |
Click Exit. |
Enter or change data in these fields:
Field Name |
Type / Max Length |
Action / Description |
Parent item no |
Display |
The selected parent item number, item type, stocking unit of measure, item status, current ECL, make/buy/kit and bypass code |
ECL |
Display |
The engineering change level of the bill of material being added or changed |
Eng drawing no |
Optional |
Accept the displayed default from the Eng drawing no field in the item's record in the Branch Item Maintenance (IMB) program or enter another drawing number. |
Eng approved? |
Display |
A check mark indicates that the bill has been approved by the engineering department |
Eng appr date |
Display |
The date this ECL was approved by the engineering department |
QA approved? |
Display |
A check mark indicates that the bill has been approved by the quality assurance department |
QA appr date |
Display |
The date this ECL was approved by the quality assurance department |
Bill audited date |
Optional |
Select the date, or enter the date shortcut when this BOM was audited. |
Bill auditor |
Optional |
Enter the name of the person who audited this BOM. |
Mfg approved? |
Display |
A check mark indicates that the bill has been approved by the manufacturing department |
Mfg appr date |
Display |
The date this ECL was approved by the manufacturing department |
Last ECO |
Display only |
The last ECO number that updated this bill of material's engineering change level. The field displays if you use ECO Maintenance to manage bill of material changes. |
Choose the appropriate options:
To |
Do This |
Delete the displayed bill of material |
Click Delete. See Delete. |
Enter notes for this ECL |
Click Notes. See Enter Notes. |
Enter data in custom fields your company uses |
Click User.
See Enter Data in User Fields or
Shadow File Fields. |
Display changes made to the bill header |
Click Audit.
See Display an Audit Trail.
Click Exit to return to
this program. |
Add or display components of this BOM |
Click Component. See Add a Component to a Bill of Material. |
Copy this bill of material to a new item or ECL |
Click Bill
copy. See Copy a Bill of Material. |
Display approval status for this BOM |
Click Approvals.
See Display Bill of Material Approval
Status. Click OK to
return to this program. |
Display changes made to the component list |
Click BOM
Audit. See Display an Audit
Trail. Click OK to
return to this program. |
Display the current routing for this parent |
Click Routing.
See Display the Routing for an Item.
Click OK to return to
this program. |
Display the last engineering change order |
Click ECO
Inq. See Enter an Engineering
Change Order for fields displayed. |
Specify a different ECL |
Click OK. See step 2. |
Exit the program |
Click Exit. |