Add a Component to a Project Bill of Material
When you click BOM in the Project Maintenance (PSM) program, you can enter, change, and copy a project bill of material, add a subassembly, add, copy, merge, and delete components. See Background and Road Map for more information.
The program displays these fields:
Field Name |
Displays |
Parent item no |
The number of a parent item of an assembly |
Item description |
The item description |
ECL |
The Engineering Change Level of the parent item *: This ECL is entered the Current ECL field in the item's record when you click Inventory and then Branch. |
Type |
New: New item for this project |
Select the parent item number and click Select.
Click Component.
Click Add if components exist.
Enter data in these fields:
Field Name |
Type / Max Length |
Action / Description |
Comp item no |
Required |
Enter the number of the component, click the Lookup icon on the left to select a component in the project or click the Lookup icon on the right and use the standard lookup options to select a component from your database. You cannot use configured product or phantom items in a project bill of materials. |
Part designator |
Optional |
Enter the identifier your company uses if this component is to be listed on this bill of material more than once. You may call this designator a balloon number, bubble number, file number, material tag, or reference number. |
Field Name |
Type / Max Length |
Action / Description |
Qty per assy |
Required |
Enter the quantity
of the component required to build one parent item. For example,
if the parent item is a table and the component is a table leg,
you would enter 4. You can enter .00000 for a component whose
usage is insignificant. |
Reference code |
Optional |
Enter a reference
that your company uses. For example, you can use this field to
associate this component with its balloon or bubble number on
the engineering drawing. |
Flr stk cd |
Required |
Accept the displayed
code, select 0 to pick
this component from on-hand inventory, or select 1
to backflush it from floor stock. |
LT offset |
Optional |
Enter the number
of days after a manufacturing order is released that the component
is required. |
Setup matl loss |
Optional |
Enter the quantity
of material that you typically lose during the setup of the operation. |
Scrap % |
Optional |
Enter the percent
of this component that you normally scrap during the manufacturing
process. The system increases
the quantity required by this scrap factor: (Quantity
ordered
x Qty per assy) + (Quantity
ordered
x Qty per assy x Scrap % x 0.1) rounded
to the nearest integer.
If your scrap factor is 5%, enter
5.00. |
Effective date |
Required |
Select the date when this component will be used for manufacturing orders, enter a date shortcut, or leave blank to use 01/01/1900. |
Expiration date |
Required |
Select the date through which this component will be used for manufacturing orders, enter a date shortcut, or leave blank to use 12/31/9999. |
Date revised |
Optional |
Accept the displayed login date, select another date, or enter a date shortcut when you revised this BOM. |
Component type |
Optional |
Enter your user-defined code for component type. This field is not used by the system, but you can use it in the custom reports. |
Operation seq no |
Conditional |
If you want to
backflush picking, enter the operation sequence number when you
want the system to pick this component. For example, if this component
is not required until the third operation, enter that sequence
number. |
Comp reference |
Optional |
Enter the reference
your company uses. |
Picking warehouse |
Optional |
The warehouse location from which the component is backflushed. |
Picking bin location |
Optional |
The bin location from which the component is backflushed. |
Replacement item? |
Optional |
Select if you replace this component under warranty or leave blank if you do not. |
Critical item? |
Optional |
Select if this
component is critical to this BOM or leave blank if it is not. |
Subs prohibited? |
Optional |
Select to prohibit the use of a substitute item for this component or leave blank to allow substitution. |
Pick per receipt? |
Optional |
Select if you want backflushed components to be rounded based on the current receipt quantity or the total received for order. See Background for more information. |
Choose the appropriate options:
To |
Do This |
Change a field |
Click Modify. |
Exit without adding this component |
Click Cancel. The program prompts Comp item no and Part designator. Enter the next component or leave blank to exit. |
Enter notes |
Click Notes. See Enter Notes. |
Accept the data |
Click OK. The program prompts Comp item no and Part designator. Enter the next component or leave blank to exit. |
Note
You cannot delete a record until it has been saved; use Cancel.
Choose the appropriate options when you click OK or Cancel:
To |
Do This |
Add another component |
Click Add. |
Delete the selected component |
Click Delete. See Delete. |
Copy a selected component |
Click Copy. See Copy a Component in a Project Bill of Material. |
Display the selected component |
Click Select. |
Display components from a specific component |
Click Restart. The program prompts Comp item no and Part designator. Enter the first component you want to display or leave blank to begin with the first component in the file. |
Print the component listing |
Click Print. See Print. |
Merge components from another project BOM or for an item in your database into this BOM |
Click Bill merge. See Merge Components from Another Bill of Material. |
Exit this bill of material |
Click Exit. The program prompts Parent item no and ECL. Enter the parent of a subassembly or leave blank to exit. |
Choose the appropriate options when you click OK or Cancel:
To |
Do This |
Add another subassembly |
Click Add. |
Delete the selected subassembly |
Click Delete. See Delete. |
Display the selected subassembly |
Click Select. |
Display items from a specific item |
Click Restart. The program prompts Parent item no and ECL. Enter the first item you want to display or leave blank to begin with the first component in the file. |
Print the item listing |
Click Print. See Print. |
Sort the item listing |
Click Sort options. Click a sort option or click Cancel to use the original sort order. |
Exit this bill of material |
Click Exit. |
Choose the appropriate options when you click Exit:
To |
Do This |
||||||||||
Change a field |
Click Modify. |
||||||||||
Delete this project |
Click Delete. The program prompts Do you want to delete this record?. Click Delete to delete this entire project or click No to retain this project. |
||||||||||
Exit without creating this project |
Click Cancel. |
||||||||||
Display additional fields |
Click Other info. |
||||||||||
Enter notes for this project |
Click Notes. See Enter Notes. |
||||||||||
Enter an item, its branch information, and costs |
Click Inventory and then:
|
||||||||||
Enter quantities, profit, commission, and discount percents |
Click Proj qtys. See Enter a Project Quantity. |
||||||||||
Enter a bill of material |
Click BOM. See Enter a Project Bill of Material. |
||||||||||
Enter a routing |
Click Routing. See Enter a Routing. |
||||||||||
Enter a new customer |
Click Customer. See Enter a New Customer. This button displays only if you entered a new customer in the Customer number field. |
||||||||||
Enter miscellaneous costs |
Click Misc costs. See Enter Miscellaneous Costs. |
||||||||||
Calculate costs for project quantities |
Click Roll up. |
||||||||||
Display the project and unit costs for project quantities |
Click Summary. See Display a Project Summary. |
||||||||||
Print documents for this project |
Click Print and then:
|
||||||||||
Transfer this project to your database |
Click Transfer. See Transfer a Project. |
||||||||||
Close this project |
Click Close proj. See Close a Project. |
||||||||||
Display the sales quote generated by this project or the sales order line if the sales quote has been transferred |
Click Order. See Enter a Sales Quotation or Display a Summarized Sales Order. This button displays only for a transferred customer project. |
||||||||||
Accept the data and exit |
Click OK. |
When you click OK or Cancel, enter another project number or exit the program.