Adjust Purchase Order Line Dates
When you click Lines and then Adj dates in the PO Maintenance (VOE) program, you can change the Date wanted or Date promised on multiple open order lines.
-
Click to select the date type you want to change.
|
Field Name |
Type / Max Length |
Action / Description |
|
Date wanted |
Required Note |
Select to change the Date wanted field on the lines you set in step 2 based on the criteria you select in step 4. |
|
Date promised |
Select to change the Date promised field on the lines you set in step 2 based on the criteria you select in step 4. |
-
Select the open lines that you want to update:
-
Accept 1 or enter the number of the first line you want to adjust in the From line field.
-
Accept 999 or enter the number of the last line you want to adjust in the To line field.
-
Select a reason that explains why you are making this change.
-
-
Select Base delivery performance on original promise date? if you want the vendor's delivery performance to be measured from the original promise date or leave blank if you want to use the new Date promised.
-
Select the adjustment criteria:
|
Field Name |
Type / Max Length |
Action / Description |
|
Change from a date to another |
Optional |
Select if you want to change one date to another date or leave blank if you do not. For example, suppose you want to change the date from April 1 to April 3. If you select this option, you must also:
If the date is April 2 or any date other than April 1, it will not be changed. |
|
Change to a specific date |
Optional |
Select if you want to change the date type to a specific date or leave blank if you do not. You must also select the date you want to use in the Change to field. For example, suppose you want to change the Date wanted to April 3 for all lines. Enter April 3 in the Change to field. All lines change to April 3, regardless of their current date. |
|
Adjust by number of days |
Optional |
Select if you want to add or subtract a number of days from the current date for the selected date type or leave blank if you do not. If you select this option, you must enter the number in the Number of days field that you want to add or subtract from the current date. For example, enter 7 to move the date out one week; if the date is the 10th, it becomes the 17th. Enter -3 to move the date in three days; if the date is the 10th, it becomes the 7th. |
-
Choose the appropriate options:
|
To |
Do This |
|
Change a field |
Click Modify. |
|
Exit without changing dates |
Click Cancel. |
|
Accept the data and make the change |
Click OK. |
-
Choose the appropriate options when you click OK or Cancel:
|
To |
Do This |
|
Add another line |
Click Add. |
|
Delete the selected PO line |
Click Delete. See Delete. This button is grayed if the line is voided or closed. |
|
Copy the selected PO line |
Click Copy. See Copy. |
|
Display the selected PO line |
Click Select. |
|
Display PO lines from a specific line |
Click Restart. The program prompts PO line number. Enter the first line you want to display or leave blank to begin the display with the first line in the file. |
|
Print the PO lines |
Click Print. See Print. |
|
Display the previous set of records in the file |
Click Page up. |
|
Display the next set of records in the file |
Click Page down. |
|
Display the extended and net amount totals for these lines |
Click Totals. Click Close to remove this data from display. |
|
Change the Date wanted or Date promised fields for multiple lines |
Click Adj dates. See Adjust Purchase Order Line Dates. |
|
Exit PO lines |
Click Exit. |
-
Choose the appropriate options when you click Exit:
|
To |
Do This |
||||||||
|
Change a field |
Click Modify. |
||||||||
|
Exit without creating the purchase order |
Click Cancel. |
||||||||
|
Change the vendor number field |
Click Other info and then Modify. This button displays before a PO number is assigned. |
||||||||
|
Enter or change notes for this purchase order |
Click Notes. See Enter Notes. |
||||||||
|
Go to a related program |
Click Jump. See Jump. |
||||||||
|
Change the vendor or ship-to address |
Click Address and then:
See Enter or Change an Address. Note |
||||||||
|
Enter PO lines |
Click Lines. See Enter a Purchase Order Line. |
||||||||
|
Display the extended and net amount totals for the purchase order |
Click Totals. Click Close to remove this data from the display. |
||||||||
|
Display previous purchases of all items from this vendor |
Click View BVI. See Display Purchase Orders by Vendor. Click Exit to return to this program. |
||||||||
|
Review you options for this program |
Click Prog opts. See Set PO Maintenance Options. |
||||||||
|
Print this purchase order |
Click Print PO. See Print or Reprint Documents. |
||||||||
|
Display the vendor's advanced shipment notice |
Click View ASN. See Display the Vendor's Advanced Shipping Notice. |
||||||||
|
Display purchase order approval status |
Click Approvals. See Display Purchase Order Approval Status. |
||||||||
|
Close this purchase order |
Click Close order. SeeClose a Purchase Order. |
||||||||
|
Enter this PO |
Click OK. |
-
Choose the appropriate options when you click OK or Cancel:
|
To |
Do This |
|
Display the selected record |
Click OK. |
|
Display the previous record in the file |
Click Prev. |
|
Display the next record in the file |
Click Next. |
|
Enter a new purchase order |
Click New. |
|
Exit the program |
Click Exit. |